Tag Archives: Harper Creek

Harper Estuary project gets started following years of discussion

Excavation started today on a $1.3-million project to reshape and restore Harper Estuary in South Kitsap.

Work began today on access roads for the Harper Estuary restoration project. Photo: Doris Small, WDFW
Heavy equipment begins work today to build access roads for the Harper Estuary restoration project.
Photo: Doris Small, WDFW

It is a project that I’ve been discussing since 2001, when former Harper resident Chuck Hower first introduced me to the idea, a concept that he had been promoting with state and federal officials. (See Kitsap Sun, Feb. 2, 2001.)

Orion Marine Contractors was the successful bidder among six companies that offered bids on the project to remove much of the fill material placed in and around the estuary. The amount of soil to be removed is estimated at more than 15,000 cubic yards, or enough to fill roughly 1,000 dump trucks.

“The work will restore (the estuary) to levels conducive to marsh establishment,” said Doris Small of the Washington Department of Fish and Wildlife. The project will recover a spit, reconnect saltwater to an impounded wetland and remove a bulkhead and old “relic” road that impounds the wetland, she said.

Continue reading

Harper Estuary project nears fall construction; bridge to come later

A new Harper Estuary bridge is being planned with a trail to the water. Graphic: Kitsap County Public Works
A new Harper Estuary bridge is being planned with a trail to the water. // Graphic: Kitsap County Public Works

The Harper Estuary restoration project is finally coming together, with one contractor being hired for culvert removal, others bidding for the excavation work and engineers completing the designs for a new bridge.

Since June, the first phase of the project has been divided into two parts. The first actual construction will involve the replacement of a 24-inch culvert that carries Harper Creek under Southworth Drive. The new structure will be a three-sided, open-bottom culvert that spans 16 feet across the stream.

A larger culvert will carry Harper Creek under Southworth Drive. Graphic: Kitsap County Public Works
A larger culvert will carry Harper Creek under Southworth Drive. (Click to enlarge.)
Graphic: Kitsap County Public Works

Bids were opened, and a contractor has been preliminarily selected, said Doris Small, project coordinator for the Washington Department of Fish and Wildlife. A meeting has been scheduled for Tuesday to iron out the final details and award the contract, she said.

The work must be completed by Oct. 15, so things will progress rapidly, she said. An announcement will be made soon regarding a temporary detour on Southworth Drive.

The remainder of the first phase involves the excavation of dirt and other debris used to fill in the estuary years ago. The project has been reduced slightly in size from the original design, reducing water contact in certain spots, Doris told me. Also, an analysis of the soils to be removed concluded that some of the fill material is contaminated at such a low level that it can be used as fill elsewhere or sent to a composting facility.

Olympiad Drive crosses Harper Estuary. Photo: Kitsap County Public Works
Olympiad Drive crosses Harper Estuary.
Photo: Kitsap County Public Works

Bids will be taken on the excavation project until Sept. 13, and the work must be done before the middle of February.

The design of a new 120-foot-long bridge on Olympiad Drive is between 60 and 90 percent complete. Applications have been submitted for several grants to complete the project, primarily construction of the new bridge. The bridge will replace a 36-inch culvert where the road crosses the estuary. The design includes access for people to walk down to the water, and it can be used to launch small hand-carried boats.

As I described in Water Ways in June, the existing makeshift boat launch must be removed to allow the restored estuary to function properly. I am told, however, that county officials are still looking for a nearby site to build a new boat launch with access for trailered boats.

If grants are approved to cover the cost, the bridge could be under construction next summer, Doris said. The total estimated cost of the entire restoration is now $7 million, with $4.1 million approved from a mitigation fund related to contamination from the Asarco smelter in Tacoma.

For information: