Skokomish restoration makes progress in federal funding arena

UPDATE: June 12, 2016
The Skokomish River ecosystem restoration project, as proposed by the Army Corps of Engineers, remains on track. The House Transportation and Infrastructure Committee on May 25 unanimously endorsed the Water Resources Development Act, which would authorize the project. The legislation must still be approved by the full House and Senate.
—–

After decades of in-depth studies and anxious waiting, restoration of the Skokomish River ecosystem took a major step forward today, when a committee of the U.S. Senate endorsed the $20-million effort as part of a larger legislative package.

Skok watershed

The Skokomish restoration was one of many projects that sailed through the Senate Environment and Public Works Committee as it passed a $9-billion authorization bill on a 19-1 vote. The bill must still be approved by the full Senate and House, but supporters of the Skokomish restoration were thrilled with the light at the end of the tunnel.

Rich Geiger, project engineer for the Mason Conservation District, has been shepherding the Skokomish effort for as long as I can remember. I asked him how it feels to finally see some action in Congress.

“It feels really really good,” he said slowly, emphasizing each word.

The restoration program consists of five separate projects along the Skokomish River. Although not designed for flood control, these projects for improving ecological health are expected to reduce flooding along one of the most frequently flooded rivers in the state.

The restoration effort has received support from far and wide. As Rich likes to point out, experts generally agree that Puget Sound cannot be restored without restoring Hood Canal, and Hood Canal cannot be restored without restoring the Skokomish River.

Sen. Patty Murray has been a strong advocate for the project.

“The waters of Hood Canal and Puget Sound are essential to the Washington state environment, economy, and our way of life,” the senator said in an email, “so I am proud to fight for investments in the restoration of the Skokomish River. This critical work will restore habitat and wetlands and improve fish passage, which in turn supports salmon recovery — all necessary to maintain our precious natural resources.”

U.S. Rep. Derek Kilmer, D-Gig Harbor, said improving the health of the Skokomish River would be a boon for Mason County and the entire region. He said he applauded the efforts of the Skokomish Watershed Action Team, the Skokomish Tribe and area residents who worked together to shape the restoration program.

“This project ensures we can better protect critical species like salmon … while restoring more natural areas for folks to explore,” Kilmer said in an email. “That will help bring more visitors to recreate in this watershed while protecting it for future generations.”

The $9-billion authorization bill, known as the Water Resources Development Act of 2016 (PDF 4.1 mb), includes money requested by the Army Corps of Engineers for water-related projects across the country. In additional to restoration efforts, the bill includes authorization of projects related to flood control, dredging, drinking water emergencies, water treatment and pipelines. For a summary of the bill see the report to the committee (PDF 284 kb).

The bipartisan endorsement and near-unanimous support offers hope that the needed money will be approved in a future appropriations bill tied to the budget, Rich Geiger told me. He is also optimistic that the 35-percent state/local match will be made available through state grants or a legislative appropriation.

“Now that have an approved plan, we are coming to Washington state with a funding request that is much larger than normal,” Geiger said. “This is a little unprecedented.”

The federal share for the project would be about $13 million and the state share nearly $7 million.

Some money has already been provided for engineering work, Rich said. If things go well, the final designs can be ready for the start of construction in October of 2019.

These four projects would come first:

Confluence levee removal: This levee was built with old cars at the confluence where the North Fork flows into the mainstem of the Skokomish. Some 5,000 feet of the levee would be removed. A small channel would be created to allow water from the mainstem to flow into the North Fork and return at the existing confluence. Large woody debris would help direct water into the channel. Estimated cost: $7.5 million.

Wetland restoration at river mile 9: The existing levee would be breached in four locations, and a new levee would be built some 200 to 300 feet farther away. The levee would allow for minor over-topping but would not increase the flood risk. Estimated cost: $2.4 million.

Wetland restoration near Grange: Larger breeches are planned for the levee near the Grange hall at river mile 7.5 to 8. A new levee, up to 10 feet tall and 2,900 feet long, would be constructed 1,200 feet farther back with no increase in flood risk. Locations are still under discussion. Estimate cost $3.3 million.

Side channel connection near Highway 101: An old remnant channel between river mile 4 and 5.6 would be restored to take water from the mainstem at high flows. Woody debris would help define the inlet and outlet to the channel, which would become a ponded wetland at low flows. Estimated cost: $3.1 million.

The fifth project would be constructed over two years in 2020-21:

Large woody debris: Upstream of the confluence with the North Fork, large woody debris would be installed. Large clusters of trees with root wads, as well as some single trees, would be placed between river mile 9 and 11, as measured from the estuary in Hood Canal. Estimated cost: $3.2 million.

The original plan for the Skokomish, as developed in an early report by the Army Corps of Engineers, called for more projects and would have cost closer to $40 million.

Some of those other projects are being funded through other programs, such as the Salmon Recovery Funding Board. For example, the reconnection of a stagnant section of Weaver Creek to the free-flowing Purdy Creek is scheduled for this summer using SRF Board money.

In addition, numerous man-made logjams are being planned to create salmon habitat, reduce sediment flows and stabilize the stream channel. Also, preliminary designs and discussions are underway to relocate Skokomish Valley Road, a main route into the Olympic Mountains. Moving the road would allow for the removal of levees, river bank restoration and a reconnection to about 60 acres of floodplain.

One thought on “Skokomish restoration makes progress in federal funding arena

  1. UPDATE: June 12, 2016
    The Skokomish River ecosystem restoration project, as proposed by the Army Corps of Engineers, remains on track. The House Transportation and Infrastructure Committee on May 25 unanimously endorsed the Water Resources Development Act, which would authorize the project. The legislation must still be approved by the full House and Senate.