Triton Marine Construction Corp. of
Bremerton has been selected to complete $9.9 million in work
at Puget
Sound Naval Shipyard & Intermediate Maintenance
Facility.
The work will be completed under a previously-awarded contract for construction of a dry dock water treatment system, according to a release from the Department of Defense.
Triton will build infrastructure at three dry docks necessary to bring the shipyard into compliance with environmental standards for capturing and treating water used for industrial processes.
The Navy received four proposals for the work. Construction will be completed in the fall of 2016.
The Bremerton contractor recently moved its headquarters to Constance Road in the Port of Bremerton’s Olympic View Industrial Park. Triton moved to Kitsap from Houston in 1999.