Mismatched downtown Bremerton sidewalk raises a question

The in basket: Mike Burton writes, “The city of Bremerton has put a lot of effort and expense into making the roads and sidewalks in the downtown area and, specifically, Pacific Avenue look very nice, and they plan to continue that north of Sixth Street on Pacific.

“As they were doing all of this,” Mike said, “the city purposely worked around a section of the sidewalk between Second Street and Burwell Avenue on the east side of Pacific. That section looks awful compared to everything else the city has done.

“Is there an explanation? Are there any plans to ‘fix’ that so that it conforms with all of the surrounding sidewalks?”

“Mostly the problem is aesthetic,” he conceded, ” but it is a bit uneven, especially where the patches and the ‘tar’ that they use for sealing meet, compared to the rest of the sidewalk around it. It just looks ridiculous, considering the city’s efforts to make all this look so nice!”

The out basket: Gunnar Fridriksson of the city engineering staff says, “That ‘sidewalk’ is actually the top for a very large vault that houses the electrical servicing the Harborside Commons garage (the old JC Penney building).

“WIth the tunnel project, we did look at trying to either have it replaced or resurfaced to make it more presentable.  Unfortunately, due to the way it was constructed, we were unable to find an economical way of doing so that met with the state’s schedule for the completion of the improvements.

“Depending on what happens with the building, there may be an opportunity in the future for improvement. ”