Is new Ridgetop traffic signal coming soon?

June 13th, 2013 by travis baker

The in basket: Robin Jensen wonders when the promised new traffic signal on Ridgetop Boulecard at the southbound off-ramp from Highway 303 will be done.

“This project is still showing on the (county’s Transportation Improvement Plan) for construction beginning this month,” he said. “Because this signal has been needed for so long, Ridgetop residents are looking for signs of construction every day. Can you confirm whether this project is scheduled to start soon?”

The out basket: Quite soon, actually. Doug Bear of Kitsap County Public Works says, “The project is out to bid with bid opening set for June 18. Work is expected to begin in July sometime. We will post more information after we open bids.

For what it’s worth, the bid specs can be seen online at http://www.kitsapgov.com/pw/pdf/CRP_3658/3658_Ridgetop_sr303_bid_inv.pdf)

The county has taken over this work at a state intersection to compensate for congestion on detours when Bucklin Hill Road closes next year for replacement of the Clear Creek bridge.

 

Tags: , , ,

Email This Post Email This Post

Leave a Reply

Before you post, please complete the prompt below.

(Not a trick question) What color is the pink house?

Available on Kindle

Road Warrior Tip

You can reach Travis Baker at tvisb@wavecable.com

Categories