What’s holding up the Noll Road roundabout in Poulsbo?

The in basket: Ellen Ross-Cardoso of Poulsbo asks, “Could you find out if the construction of the unneeded roundabout at Lincoln and Noll in Poulsbo is ever going to end?

“According to the signs it was supposed to have been completed September 1, and more than three months later they’re still out there screwing with it. Is this a lot more complicated than it seems, or is there no meaningful work out there for county road crews?”

The out basket: It is actually a city of Poulsbo project, with a little financial participation from the county.

Mike Lund, the city’s senior field inspector, says, “The Noll Road Roundabout Project is just about complete. The contractor, RV Associates, has a few more punch list items to complete and the project will be over.

“The project was scheduled to be completed October 15 (though the construction sign said Sept. 30). The contractor has been working on completing the punch list items since mid-October but between the bad weather and scheduling of subcontractors, it has taken longer than expected.

“The workers your reader saw onsite are actually part of the contractors and subcontractors work force. The city of Poulsbo has an inspector that is onsite as needed but not full time now.

“RV Associates has done a good job on this project,” Mike said. “Unfortunately some things just take a little longer than expected. The project will be completed by the end of next week and the project will be completed under budget.”

 